We have received information from Bellway in relation to remedial works required to the road areas that will eventually be adopted by Essex Highways. The timelines are as follows:

  1. RDR: Work commenced on the 10th May 2021 with planned completion by Friday 21st May 2021;
  2. Aqua Verde: Work to commence Monday 17th May 2021 through to Friday 28th May 2021;
  3. Eagle Rise: Work to commence Tuesday 1st June 2021 completing on Saturday 12th June 2021.

Bellway will be using the nursery site as their compound area throughout the above periods.