We have received notification that Bellway are negotiating with Essex Highways and their contractor to finish off remedial works across Eagle Rise & Aqua Verde (which will include installation of speed limit signs and traffic calming features) plus all remaining items relating to the Radial Distributor Road signals and Bus Gate.
In addition Surface Water Drains still require adoption and once the sewers have been adopted, charges for surface water drainage from Anglian Water will be applicable.
At present Bellway are looking at an 8 week programme to completion with all works being finished on site close to Easter.